Refurbishment of pumping stations SP-1, SP-2, and SP-6

Location

Baie-Comeau, QC

Timeframe

2017

Description

Deric Construction was responsible for refurbishing 3 pumping stations (SP-1, SP-2, and SP-6) and installing new pumps. The project also involved mechanical, electrical, and automation work.

Main features

  • Installed control panels
  • Installed baffles at the overflow
  • Installed 250 and 335 HP pumps
  • Shut down and isolated the three pumping stations
  • Dismantled equipment
  • Worked on instrumentation and installed wall valves, screen baskets, guide bars, and pump accessories
  • Connected and commissioned the pumping stations
Privacy policy
  • Head office
    5145, rue Rideau Québec, QC G2E 5H5 T 418 781-2228
  • Montreal office
    1100 Montée Masson Laval, QC, H7C 0J4 T 514 685-8989
  • Ontario office
    3-4055 Harvester Road Burlington, ON L7L 5Z7 T 905-631-9644
  • GIDC Mécatina
    Navco Nord 6, Rte Mécatina C. P. 156 La Tabatière, QC G0G 1T0 T 418 773-2659 | F 418 773-2526