System Upgrade

Location

Saint-Basile-de-Portneuf, QC

Timeframe

2020

Description

As part of this project, Fugère et Fils, newly named Deric Construction, upgraded 31 conveyors. Over 6 weeks, we mobilized 17 workers and proceeded to the replacement of rollers, chains and belts, to the modification of chutes, in addition to oil and grease changes.

Main features

  • Inspection of each conveyor
  • Maintenance on 31 conveyors
  • Replacement of support rollers, impact rollers and return rollers on various conveyors
  • Adjustment of belts and belt scrapers on various conveyors
  • Alignment and adjustment of belts on various conveyors
  • Adjustment of the head scraper and the tail scraper on some conveyors 
  • Cleaning of conveyors

Repairs to the anchors of docks 105 and 106