System Upgrade
Location
Saint-Basile-de-Portneuf, QC
Timeframe
2020
Description
As part of this project, Fugère et Fils, newly named Deric Construction, upgraded 31 conveyors. Over 6 weeks, we mobilized 17 workers and proceeded to the replacement of rollers, chains and belts, to the modification of chutes, in addition to oil and grease changes.
Main features
- Inspection of each conveyor
- Maintenance on 31 conveyors
- Replacement of support rollers, impact rollers and return rollers on various conveyors
- Adjustment of belts and belt scrapers on various conveyors
- Alignment and adjustment of belts on various conveyors
- Adjustment of the head scraper and the tail scraper on some conveyors
- Cleaning of conveyors

Repairs to the anchors of docks 105 and 106