Replacement of inflatable supers at Windsor Dam

Location

Windsor, Québec

Timeframe

2017

Description

The project consisted of work for the de-installation of the existing supers, handling and finally the installation of the new supers that were supplied by the client.

Main features

  • Increase 1: Decommissioning of existing fusegates. Cleaning and preparation for new installation. Installation of the new fusegate and commissioning and testing;
  • Increase 2: Dismantling of the existing fusegates. Cleaning and preparation for the new installation. Installation of the new fusegate and commissioning and testing;
  • Increase 3: Dismantling of the existing fusegates. Cleaning and preparation for the new installation. Installation of the new fusegate and commissioning and testing;
  • Fusegates 4-A and 4-B: Dismantling of the existing fusegates. Cleaning and preparation for the new installation. Installation of the new fusegate and commissioning and testing;
  • Installation of a work cofferdam;
  • Repair of concrete surfaces;
  • Formwork and concreting of new concrete supports for the new fusegates.

Design and installation of instrumentation, control, and automation systems