Replacement of the rails of gantry cranes 5, 7 and 8

Location

Quebec City, QC

Timeframe

5 weeks in 2017 (Cranes 7 and 8) and in 2020 (Crane 5)

Description

During this project, Fugère et Fils, newly named Deric Construction, had to remove each section of rail and then rebuild the foundations and reinstall new rails with new clamps. Millimetre accuracy was required and space for welding was very limited. The rails for gantry cranes 7 and 8 were replaced in 2017, followed by the rail of crane 5 in 2020. Both projects had a tight schedule.

Main features

  • Remove each section of rail
  • Rebuild the foundations and reinstall new rails with new clamps 
  • Change of rail gauge and new rails
  • Air carbon arc gouging work
  • Welding and grinding work
  • Work at heights, over water, more than 150 feet from the ground