Description
This project involved producing and installing new fire lines (10″ on main lines and 4″ on vertical lines) for tanks 7 and 8. It also consisted of installing foam boxes, piping and supports for the TK-08 tank.
Main features
- Located underground pipelines
- Fabrication and installation of pipe supports
- Fabrication of the main foam manifold
- Installation of supports, piles and welding work on piles
- Fabrication and installation of piping
- Welding work on TK-07 and TK-08
- Modification of the flanges for the foam boxes
- Installation of 4 new foam chambers on TK-07 and TK-08
- Paint touch-up work
- Hydrostatic test