Fabrication and installation of a foam line for tanks TK-07 and TK-08

Location

Quebec City, QC

Timeframe

2018

Description

This project involved producing and installing new fire lines (10″ on main lines and 4″ on vertical lines) for tanks 7 and 8. It also consisted of installing foam boxes, piping and supports for the TK-08 tank.

Main features

  • Located underground pipelines
  • Fabrication and installation of pipe supports
  • Fabrication of the main foam manifold
  • Installation of supports, piles and welding work on piles
  • Fabrication and installation of piping
  • Welding work on TK-07 and TK-08
  • Modification of the flanges for the foam boxes
  • Installation of 4 new foam chambers on TK-07 and TK-08
  • Paint touch-up work
  • Hydrostatic test

Piping – Ste-Foy WTP

Visitez le détail de ce projet
Privacy policy