As part of this project, Cribtec increased the electrical distribution capacity of the Anse au Foulon terminal of the Port of Quebec by 1.5 MW.

Main features

  • Construction of two new 25 kV/600 V substations with a 2.5 MVA capacity, including power and telecommunications wiring
  • Installation of new overhead and underground lines and their interconnection with the Hydro-Quebec’s network
  • Carrying out all studies required by Hydro-Quebec (harmonic, etc.), as well as arc flash studies and training